“ Our Walk by Faith…”
has allowed the Building Committee to complete these activities over the past year:
- 3/5/09 - Religious Zoning was approved and granted by Fairfax County to build the new edifice
-
7/23/09 - Virginia Storm Water Management Permit was approved and granted
-
7/23/09 – Fairfax County Attorney signature was received to record our “Deed of Easement” with no liens against the property
-
8/5/09 – Fairfax County “Critical Structures” Meeting was completed and we obtained the County’s approval to pursue the Demolition and Building Permits
-
8/6/09 – Fairfax County approved the “Site Plans” and granted HFC the Site Permits
-
9/12/09 – HFC Board Approval to pursue the “Commitment of Financing”
-
10/6/09 – Virginia Department of Transportation (VDOT) granted HFC the “Lane Usage Permit”
-
10/22/09 – Fairfax County approved and granted HFC our Demolition and Building Permits
-